Brackenhurst BuildersRidgeview mechanical package

Theme
Ask Dominic

Submittals and RFIs

Every pending item against the 10 business day window. Two submittals sit past it, both with the design team, and both hold up equipment delivery dates.

Response review, updated Sep 28, 2026
A project engineer reviewing submittals with a design team at a jobsite

How long each item has waited

State on Sep 28, 2026 2 submittals past the 10 business day window Oldest 13 business days

Every pending submittal and open RFI on the Ridgeview Medical Office Building mechanical package, with the business days it has waited against the 10 business day response window, whose court it sits in, and what has to happen to get the air handling unit submittal at revision 2 answered. Prepared weekly by the Ironvale project engineer for the Brackenhurst Builders project manager and the design team.

Since Aug 20, Ironvale Mechanical has logged 18 submittals and 11 RFIs, 29 items in all. Twenty-two are answered. Seven are pending: 4 submittals and 3 RFIs. Two of the pending submittals are past the window, and both sit with the design team.

Answered2214 of 18 submittals, 8 of 11 RFIs
Pending74 submittals, 3 RFIs
Past the window2Both submittals

The window is 10 business days. The bars count business days from the day the item was logged as submitted to Sep 28. Anything above 10 is past the window. The air handling unit submittal at revision 2 is highlighted at 13 business days, and the hydronic pumps submittal follows at 11.

Live from the Dashboards appOpen the full report

Submittals by state

Each square is one submittal. Fourteen are answered, 2 are pending inside the window and 2 are pending past it.

Live from the Dashboards appOpen the full report

Pending items and whose court they sit in

Waiting days are business days at Sep 28. The window ends 10 business days after the item was logged. RFIs are marked in the item name.

ItemDrawing or specWaitingWindow endsCourtState
Air handling unit, revision 2Spec 23 73 00, sheet M-50113Sep 23Design team, mechanical engineerPast the window
Hydronic pumpsSpec 23 21 23, sheet M-40111Sep 25Design team, mechanical engineerPast the window
Roof curb elevation, RFISheets A-301 and M-1017Oct 1Design team, architectInside the window
Variable air volume boxesSpec 23 36 006Oct 2Design team, mechanical engineerInside the window
Plumbing fixturesSpec 22 40 004Oct 6Brackenhurst, review before it goes to the design teamInside the window
Fire damper access, RFISheet M-2024Oct 6Ironvale, sketch requested by the design teamInside the window
Slab sleeve locations, RFISheet S-2012Oct 8Brackenhurst, structural engineer through the project managerInside the window

Four items sit with the design team, two with Brackenhurst and one with Ironvale. The roof curb elevation RFI reaches the end of its window on Oct 1, so it is the next item to turn red if no answer comes back.

The ceiling grid RFI is counted among the 8 answered RFIs as of the date of the email, but that answer went by email to the foreman and was never recorded, so it is not a field instruction until Brackenhurst resends it through the record. The field followed a response the office had not seen. Dominic Ostrowski ruled that only the recorded response is the field instruction, and he asked Brackenhurst to resend the answer through the record.

The response window

Window
10 business days from the day the item is logged as submitted. Weekends and site holidays do not count.
Revisions
A resubmitted revision starts a new count. The 13 business days on the air handling unit are for revision 2, submitted Sep 9.
Recorded response
Only a response returned through the record stops the clock and counts as a field instruction. An email or a phone answer does not.
Incorporated in the field plan
Ironvale marks an answer as incorporated only after the foreman and the project engineer have updated the field plan with the revision that governs.
Past the window
Named in this review with the court it sits in, the work it holds up and the date the answer is needed.

"An answer that is not in the record is not an instruction. The crew follows the recorded response and nothing else."

Dominic Ostrowski, Project manager, Ironvale Mechanical

Past the window

Answered so far

RFIs answered, 8 of 11

Live from the Dashboards appOpen the full report

Next actions

Before the Oct 9 look-ahead meeting

  • Review the 7 pending items at the Sep 28 log. Owner: Ironvale project engineer, donedone
  • Get a recorded answer on the air handling unit at revision 2. Owner: Dominic Ostrowski with the Brackenhurst project manager, Oct 8open
  • Get a recorded answer on the hydronic pumps. Owner: Dominic Ostrowski with the Brackenhurst project manager, Oct 8open
  • Chase the roof curb elevation RFI at the end of its window. Owner: Ironvale project engineer, Oct 1open
  • Send the sketch the design team asked for on fire damper access. Owner: Ironvale project engineer, Oct 2open
  • Resend the ceiling grid answer through the record. Owner: Brackenhurst project manager, Oct 2open
  • Update the field plan with each answer once it is recorded. Owner: Marguerite Toussaint, within 1 business day of each answeropen

Who is on this review

  • Dominic OstrowskiProject manager, Ironvale Mechanical, rules on the field instruction

  • Marguerite ToussaintProject operations manager, Ironvale Mechanical, keeps the log and the field plan current

  • Anjali VenkataramanProject executive, Brackenhurst Builders, escalates to the design team