The nine change events
State on Sep 28, 2026 2 events waiting on Brackenhurst Work stopped on the duct conflict
Each change event logged on the Ridgeview Medical Office Building mechanical package, with its estimate, the hours already worked and the decision Brackenhurst Builders has to make, so the concealed duct conflict is authorized or declined before more hours are spent. Prepared by Dominic Ostrowski, Ironvale Mechanical project manager, for the Brackenhurst project manager and Anjali Venkataraman.
Nine change events have been logged since mobilization. Five are authorized, 2 are declined and 2 wait on a Brackenhurst decision. The working rule is plain: no extra work before written authorization.
The table lists every event with its decision, its estimate and the hours crews worked before the decision. Eight events show 0 hours. One shows 14.
Five authorized, two declined
Authorized events are priced, approved inside Ironvale and approved in writing by Brackenhurst. Their work orders show where the work stands.
| Change event | Work order | Estimate | Work order status | Customer approval |
|---|---|---|---|---|
| Rooftop unit curb adapters | WO-3101 | $12,400 | On site | Approved |
| Hydronic isolation valves | WO-3102 | $9,800 | Complete | Approved |
| Exhaust fan riser relocation | WO-3103 | $7,100 | Ready to review | Approved |
| Condensate pump addition | WO-3104 | $5,600 | Scheduled for Oct 5 | Approved |
| Floor drain addition | WO-3105 | $3,700 | Complete | Approved |
| Pipe insulation upgrade | WO-3106 | $2,200 | No work performed | Declined |
| Access panels addition | WO-3107 | $1,500 | No work performed | Declined |
The five authorized events total $38,600. The two declined events were priced at $2,200 and $1,500, and no crew time went into either. The rooftop unit curb adapters are a separate matter from the rooftop unit curb supply question: the adapters are authorized, and the supply question sits in the scope review with Anjali Venkataraman.
From logged to authorized
Of 9 events logged, 2 were declined and 2 are still waiting, which leaves 5 authorized. The waiting two are the only events that can still change the authorized total.
Decision states
- Event logged
- The foreman or the project manager has recorded the condition with field photos and the contract scope it touches. No price yet.
- Pricing
- The project manager builds the estimate from labor and material input. Crews do not start work on a priced event.
- Internal approval
- Dominic Ostrowski approves the price and the schedule effect before it goes to Brackenhurst.
- Customer decision
- Brackenhurst accepts, declines or asks a question in writing. The answer is recorded on the work order.
- Authorized or declined
- Authorized releases the field task. Declined closes it and the crew does not start.
- Waiting for the customer
- Priced and sent to Brackenhurst, with no written answer yet. No crew hours go on it until the answer is recorded.
The concealed duct conflict
The second waiting event is the thermostat wiring relocation, WO-3109, estimated at $3,200. Its status is New and its owner is Marguerite Toussaint. No work starts on it until Brackenhurst decides.
How an event moves
- Event loggedField photos and the contract scope it touches
- PricedBuilt from labor and material input
- Internal approvalDominic approves the price and the schedule effect
- Customer decisionAuthorize, decline or ask a question in writing
- Authorized or declinedAuthorized releases the field task, declined closes it
Authorization steps for the duct conflict
- Found Sep 22, event logged
- Priced at $7,450
- Internal approval, work stopped
- Customer decision, Thursday meeting
- Decision recorded by Oct 6
- Crew released or event closed
Before work on the duct conflict restarts
- Price the change and stop further work. Owner: Dominic Ostrowski, donedone
- Decide authorization at the Thursday meeting. Owner: Anjali Venkataraman, Thursdayopen
- Record the authorization or decline in writing on WO-3108. Owner: Anjali Venkataraman, Oct 6open
- Release the crew on authorization, or close the event on a decline. Owner: Marguerite Toussaint, within 1 business day of the recordopen
- Decide the thermostat wiring relocation, WO-3109. Owner: Anjali Venkataraman, next Brackenhurst meetingopen
Decision record
- Anjali VenkataramanProject executive, Brackenhurst Builders, signs the customer decision
- Dominic OstrowskiProject manager, Ironvale Mechanical, prices and approves the event
- Marguerite ToussaintProject operations manager, Ironvale Mechanical, dispatches the crew after the decision
| Event | Customer decision | Signed by | Date |
|---|---|---|---|
| Concealed duct conflict, WO-3108 | Pending | Anjali Venkataraman | Record by Oct 6 |
| Thermostat wiring relocation, WO-3109 | Pending | Anjali Venkataraman | Not yet set |