Brackenhurst BuildersRidgeview mechanical package

Theme
Ask Dominic

Change events

Nine events logged, two waiting on you. The concealed duct conflict is decided at today's meeting and recorded by Oct 6.

Change sheet, updated Sep 28, 2026
Two project managers discussing a duct conflict in an unfinished ceiling space

The nine change events

State on Sep 28, 2026 2 events waiting on Brackenhurst Work stopped on the duct conflict

Each change event logged on the Ridgeview Medical Office Building mechanical package, with its estimate, the hours already worked and the decision Brackenhurst Builders has to make, so the concealed duct conflict is authorized or declined before more hours are spent. Prepared by Dominic Ostrowski, Ironvale Mechanical project manager, for the Brackenhurst project manager and Anjali Venkataraman.

Nine change events have been logged since mobilization. Five are authorized, 2 are declined and 2 wait on a Brackenhurst decision. The working rule is plain: no extra work before written authorization.

Events logged9Since mobilization
Authorized$38.6K5 events
Waiting for the customer2Duct conflict, thermostat wiring
Hours before authorization14 hoursConcealed duct conflict

The table lists every event with its decision, its estimate and the hours crews worked before the decision. Eight events show 0 hours. One shows 14.

Live from the Dashboards appOpen the full report

Five authorized, two declined

Authorized events are priced, approved inside Ironvale and approved in writing by Brackenhurst. Their work orders show where the work stands.

Change eventWork orderEstimateWork order statusCustomer approval
Rooftop unit curb adaptersWO-3101$12,400On siteApproved
Hydronic isolation valvesWO-3102$9,800CompleteApproved
Exhaust fan riser relocationWO-3103$7,100Ready to reviewApproved
Condensate pump additionWO-3104$5,600Scheduled for Oct 5Approved
Floor drain additionWO-3105$3,700CompleteApproved
Pipe insulation upgradeWO-3106$2,200No work performedDeclined
Access panels additionWO-3107$1,500No work performedDeclined

The five authorized events total $38,600. The two declined events were priced at $2,200 and $1,500, and no crew time went into either. The rooftop unit curb adapters are a separate matter from the rooftop unit curb supply question: the adapters are authorized, and the supply question sits in the scope review with Anjali Venkataraman.

From logged to authorized

Of 9 events logged, 2 were declined and 2 are still waiting, which leaves 5 authorized. The waiting two are the only events that can still change the authorized total.

Live from the Dashboards appOpen the full report

Decision states

Event logged
The foreman or the project manager has recorded the condition with field photos and the contract scope it touches. No price yet.
Pricing
The project manager builds the estimate from labor and material input. Crews do not start work on a priced event.
Internal approval
Dominic Ostrowski approves the price and the schedule effect before it goes to Brackenhurst.
Customer decision
Brackenhurst accepts, declines or asks a question in writing. The answer is recorded on the work order.
Authorized or declined
Authorized releases the field task. Declined closes it and the crew does not start.
Waiting for the customer
Priced and sent to Brackenhurst, with no written answer yet. No crew hours go on it until the answer is recorded.

The concealed duct conflict

The second waiting event is the thermostat wiring relocation, WO-3109, estimated at $3,200. Its status is New and its owner is Marguerite Toussaint. No work starts on it until Brackenhurst decides.

How an event moves

  1. Event loggedField photos and the contract scope it touches
  2. PricedBuilt from labor and material input
  3. Internal approvalDominic approves the price and the schedule effect
  4. Customer decisionAuthorize, decline or ask a question in writing
  5. Authorized or declinedAuthorized releases the field task, declined closes it
Live from the Dashboards appOpen the full report

Authorization steps for the duct conflict

  1. Found Sep 22, event logged
  2. Priced at $7,450
  3. Internal approval, work stopped
  4. Customer decision, Thursday meeting
  5. Decision recorded by Oct 6
  6. Crew released or event closed

Before work on the duct conflict restarts

  • Price the change and stop further work. Owner: Dominic Ostrowski, donedone
  • Decide authorization at the Thursday meeting. Owner: Anjali Venkataraman, Thursdayopen
  • Record the authorization or decline in writing on WO-3108. Owner: Anjali Venkataraman, Oct 6open
  • Release the crew on authorization, or close the event on a decline. Owner: Marguerite Toussaint, within 1 business day of the recordopen
  • Decide the thermostat wiring relocation, WO-3109. Owner: Anjali Venkataraman, next Brackenhurst meetingopen

Decision record

  • Anjali VenkataramanProject executive, Brackenhurst Builders, signs the customer decision

  • Dominic OstrowskiProject manager, Ironvale Mechanical, prices and approves the event

  • Marguerite ToussaintProject operations manager, Ironvale Mechanical, dispatches the crew after the decision

EventCustomer decisionSigned byDate
Concealed duct conflict, WO-3108PendingAnjali VenkataramanRecord by Oct 6
Thermostat wiring relocation, WO-3109PendingAnjali VenkataramanNot yet set

The live page in FuseBase

This document as a FuseBase page, read-only from the Ironvale Mechanical workspace. Changes made there appear here.
Open the page