Brackenhurst BuildersRidgeview mechanical package

Theme
Ask Dominic

Ridgeview decision room with Ironvale Mechanical

Five decisions are owed. The first is at today's meeting.

Ironvale recommends and you decide. Two change events wait on you, one with further work stopped. The rooftop unit curbs have been questioned for 16 days, and closeout runs to substantial completion on Nov 20. Records as of Monday, Sep 28.

0 of 5 decided. Next: the duct conflict at the owner meeting, 08:00 today
Two project managers reviewing work on a new office building
Answers owed by Brackenhurst
5

Scope, responses, changes, progress and closeout

Change events waiting
2

$7,450 plus $3,200, calculated from the two prices

Longest open question
16 days

Rooftop unit curbs, answer by Oct 7

Substantial completion
Nov 20

27 closeout items, 2 accepted

Decision at today's owner meeting

Concealed duct conflict, WO-3108

Crews found it in the third floor ceiling space on Sep 22 and logged 14 hours before it was priced. Ironvale recommends a written answer at the meeting, authorize or decline, and does not assume which.

Price
$7,450
Hours logged first
14
Record by
Oct 6

Decision sheet

Options and prices

What is decided, who answers, by when, what Ironvale recommends and what waiting costs. The path on the left follows this order.

DecisionWho answersBy whenIronvale recommendsIf it waits
Three sold scope lines questioned, led by the rooftop unit curbsAnjali Venkataraman, with the roofing contractorOct 7Settle the curb supply first. Dominic confirmed what Ironvale sold from the proposal.The curb order and the other rooftop unit lines wait on a recorded answer. 12 of 14 are confirmed.
Two submittals past the response windowThe design team, asked by the Brackenhurst project managerOct 8Ask for a recorded response on the air handling unit at revision 2 and on the hydronic pumps.Ironvale cannot confirm equipment delivery dates for the mechanical rooms.
Two change events waiting: WO-3108 at $7,450 and WO-3109 at $3,200Anjali VenkataramanToday for WO-3108, recorded by Oct 6. WO-3109 date not setA written answer on each, authorize or decline.No hours go on either event, and the third floor ceiling space stays as it is.
Second-floor piping, held at a verified 52 percent against a field estimate of 60Marguerite Toussaint reconciles, Dominic Ostrowski publishes, you read itOct 9Publish the reconciled count, never the 60 percent estimate.The update keeps naming the milestone as held until the figure is reconciled.
27 closeout items to accept, 2 accepted so farThe Brackenhurst closeout coordinator, for Anjali Venkataraman5 business days from each item receivedAccept each item or return it with the exact deficiency.Final payment waits on all 27 items accepted before Nov 20.

Where the record stands

Change events

From the project controls record of Sep 28. Block dates move forward each week with the demo data.

Live from the Dashboards appOpen the full report
Live from the Dashboards appOpen the full report

Key dates

DateWhat happensOwner
Thu Oct 1Owner meeting at 08:00: the duct conflict is decidedAnjali Venkataraman
Fri Oct 2Ceiling grid answer resent through the record. All eight closeout requests go outBrackenhurst project manager, Marguerite Toussaint
Tue Oct 6Duct conflict answer written on WO-3108Anjali Venkataraman
Wed Oct 7Curb supply settled with the roofing contractor. Crane and venting confirmedAnjali Venkataraman, Brackenhurst
Thu Oct 8Coordination meeting. Recorded answers due on the air handling unit and the pumpsBrackenhurst project manager
Fri Oct 9Look-ahead meeting. Update carries the reconciled piping percentageDominic Ostrowski
Fri Nov 20Substantial completionBrackenhurst and Ironvale

Recent activity

Questions and files
  • Marguerite refreshed the recordScope, submittals, change events and closeout counts as of Sep 28.
  • Four milestones published, piping heldVerified from counted quantities. The 60 percent estimate was not published.
  • Two warranty certificates returnedThe rooftop unit and hydronic pump certificates list the wrong start date. Corrected copies due Oct 16.
  • Second-floor piping countedHangers and welded joints counted with the site superintendent: 52 percent.
  • Concealed duct conflict foundThird floor ceiling space. Crews logged 14 hours before it was priced.

Your project manager: Dominic Ostrowski

Dominic prices changes, rules on the field instruction and decides whether a closeout item is sufficient. Ask before you answer; the reply stays with the decision.

  • Marguerite ToussaintProject operations manager, Ironvale, owns the RFI, submittal, change and closeout queues
  • Anjali VenkataramanProject executive, Brackenhurst, authorizes changes and accepts closeout items