Two change events wait on a Brackenhurst answer. Each answer has a price and a consequence. Ironvale recommends a written answer on both, and you decide.
Concealed duct conflict, WO-3108
$7,450Found in the third floor ceiling space on Sep 22 and priced by Dominic. Further work on it is stopped, and crews logged 14 hours before the price existed. You decide at today's owner meeting and the answer is written on the work order by Oct 6.
Answer A
Authorize at $7,450
Ironvale releases the field task and the crew returns to the ceiling space within 1 business day of the written record.
- Authorized total moves from $38,600 to $46,050
- Whether the 14 hours already logged are part of the $7,450 is decided in the same answer. Ironvale does not assume they are.
- Written on WO-3108 by Oct 6
Answer B
Decline
The event closes and the crew does not start.
- Authorized total stays at $38,600
- Closing the event does not resolve the conflict, so the ceiling space stays as it is until another answer is recorded
- The written answer also says how the 14 hours already logged are treated
A third answer is allowed: ask a question in writing first. The event then keeps waiting, no hours go on it and the ceiling space stays as it is until the answer is recorded.
Thermostat wiring relocation, WO-3109, $3,200
- AuthorizeIronvale releases the field task. On its own the authorized total becomes $41,800, and $49,250 if the duct conflict is authorized as well.
- Price
- $3,200
- Hours so far
- 0
$3,200 more
- DeclineThe event closes and the crew does not start. The authorized total is unchanged.
- Price
- $3,200
- Hours so far
- 0
No change
No work starts on WO-3109 until you decide. Its decision date is not set; it can go to the next Brackenhurst meeting.
What the authorized total becomes
Calculated from the record of Sep 28: $38,600 authorized across 5 events, plus the prices above.
| Answer | Authorized total | Change from today |
|---|---|---|
| Today, 5 events authorized | $38,600 | None |
| Authorize the duct conflict only | $46,050 | $7,450 more |
| Authorize the thermostat wiring only | $41,800 | $3,200 more |
| Authorize both | $49,250 | $10,650 more |
| Decline both | $38,600 | None |
Change events on the record
Change eventsFrom the project controls record. Block dates move forward each week with the demo data.
Ridgeview mechanical results
The full report from the project controls record: scope, responses, change events, progress and closeout.The other four answers carry no price
Decision sheet- Sold scope questionsCurb supply settled with the roofing contractor, crane and venting confirmedOct 7
- Two submittals past the windowRecorded responses on the air handling unit and the pumpsOct 8
- Held piping milestoneThe reconciled count goes in the updateOct 9
- Closeout acceptanceEach received item accepted or returned within 5 business daysOpen