
Items by type and state
State on Sep 28, 2026 8 items not yet requested 2 certificates returned
All 27 closeout items for the Ridgeview Medical Office Building mechanical package, tracked from vendor request to Brackenhurst Builders acceptance ahead of substantial completion on November 20, with the eight items not yet requested and the two warranty certificates returned for a wrong start date. Prepared by the Ironvale project engineer for the Brackenhurst closeout coordinator and the Ironvale vendors.
Closeout covers four kinds of item: warranties, as-built drawings, training records and punch items. Of the 27, 11 are received, 6 are in internal review, 2 are accepted by Brackenhurst and 8 are required but not yet requested from vendors. Final payment is ready only when all 27 are accepted.
Each row of the grid is a kind of closeout item and each column is a state. The darker the square, the more items sit there. As-built drawings carry the most items not yet requested (3), and no warranty or punch item is accepted yet.
Accepted so far
Two of the 27 items are accepted: the underslab plumbing as-built drawing and the rooftop unit operator training record. Substantial completion is November 20, so the other 25 have 7 weeks to move from where they are today.
The 27 items
The vendor column names who owes the document. Ironvale field crew means the Ridgeview crew foreman and crew. Requested dates are the dates the request went to the vendor.
Warranties, 8
| Item | Vendor | Requested | State |
|---|---|---|---|
| Rooftop unit warranty | Rooftop unit manufacturer | Sep 8 | Received, returned |
| Hydronic pump warranty | Pump manufacturer | Sep 8 | Received, returned |
| Variable air volume box warranty | Air handling and VAV manufacturer | Sep 14 | Received |
| Plumbing fixture warranty | Plumbing fixture supplier | Sep 14 | Received |
| Controls and sensor warranty | Controls vendor | Sep 14 | In internal review |
| Pipe insulation workmanship warranty | Insulation subcontractor | Sep 16 | In internal review |
| Air handling unit warranty | Air handling and VAV manufacturer | Not yet | Not yet requested |
| Water heater warranty | Plumbing fixture supplier | Not yet | Not yet requested |
The rooftop unit and hydronic pump certificates were returned on Sep 25 because each lists the wrong start date. The air handling unit warranty is not requested because its submittal at revision 2 is not yet answered. The pump, variable air volume box and plumbing fixture warranties arrived while their submittals are still pending, so they are received for review only.
As-built drawings, 7
| Item | Vendor | Requested | State |
|---|---|---|---|
| Underslab plumbing as-built | Ironvale field crew | Sep 1 | Accepted |
| Exhaust fan riser as-built markup | Ironvale field crew | Sep 24 | In internal review |
| First-floor ductwork as-built | Ironvale field crew | Sep 14 | Received |
| Rooftop unit layout as-built | Ironvale field crew | Sep 14 | Received |
| Controls as-built drawings | Controls vendor | Not yet | Not yet requested |
| Hydronic piping as-built | Ironvale field crew | Not yet | Not yet requested |
| Plumbing riser as-built | Ironvale field crew | Not yet | Not yet requested |
Dominic Ostrowski reviews the exhaust fan riser markup. Expect the controls vendor to hold its as-builts until its own invoice is paid; Marguerite Toussaint sends the request by Oct 2.
Training records, 6
| Item | Vendor | Requested | State |
|---|---|---|---|
| Rooftop unit operator training record | Rooftop unit manufacturer | Sep 8 | Accepted |
| Air handling and VAV operator training record | Air handling and VAV manufacturer | Sep 14 | Received |
| Plumbing fixture and water heater care record | Plumbing fixture supplier | Sep 14 | Received |
| Controls operator training record | Controls vendor | Sep 14 | Received |
| Test and balance briefing record | Test and balance contractor | Sep 16 | In internal review |
| Pump and drive operator training record | Pump manufacturer | Not yet | Not yet requested |
Punch items, 6
| Item | Vendor | Requested | State |
|---|---|---|---|
| Level 1 mechanical room punch list | Ironvale field crew | Sep 21 | Received |
| Rooftop equipment labeling punch list | Ironvale field crew | Sep 21 | Received |
| Level 2 ceiling space punch list | Ironvale field crew | Sep 24 | In internal review |
| Plumbing fixture trim punch list | Plumbing fixture supplier | Sep 24 | In internal review |
| Pipe insulation and labeling punch list | Insulation subcontractor | Not yet | Not yet requested |
| Test and balance deficiency punch list | Test and balance contractor | Not yet | Not yet requested |
What counts as accepted
- Required
- The item is named in the contract closeout requirements, with its source and the version that counts.
- Requested
- Ironvale has sent the request to the vendor or the crew with a due date. The state shows Not yet requested until then.
- Received
- A document has arrived. It is not yet judged.
- In internal review
- Dominic Ostrowski checks the document against the requirement. If it falls short, it goes back with the exact deficiency.
- Accepted by Brackenhurst
- Brackenhurst accepts the named item, through its closeout coordinator for Anjali Venkataraman. Only this state counts toward final payment.
- Final payment readiness
- All 27 items accepted, punch items complete and the closeout binder issued. Dominic Ostrowski and Brackenhurst agree that closeout is complete.
The eight items nobody has asked for yet
Vendor requests this week
Before the Oct 16 check
- Review all 27 items by type and state at the Sep 28 record. Owner: Ironvale project engineer, donedone
- Request the air handling unit warranty and the water heater warranty with due dates. Owner: Marguerite Toussaint, Oct 2open
- Request the controls, hydronic piping and plumbing riser as-builts. Owner: Marguerite Toussaint, Oct 2open
- Request the pump and drive operator training record. Owner: Marguerite Toussaint, Oct 2open
- Request the pipe insulation and test and balance punch lists. Owner: Marguerite Toussaint, Oct 2open
- Confirm the controls vendor invoice status. Owner: Ironvale controller, Oct 9open
- Receive the two corrected warranty certificates. Owner: Dominic Ostrowski, Oct 16open
- Accept or return each received item with the exact deficiency. Owner: Brackenhurst closeout coordinator, within 5 business days of each itemopen
What the record says
Who is on this tracker
- Dominic OstrowskiProject manager, Ironvale Mechanical, reviews every received document
- Marguerite ToussaintProject operations manager, Ironvale Mechanical, sends the vendor requests
- Anjali VenkataramanProject executive, Brackenhurst Builders, accepts the named closeout items
