What Ironvale needs from Brackenhurst to close the open answers, why, and by when. Upload straight into the request.
- Ceiling grid RFI answer, resent through the recordBrackenhurst project manager. The email answer went to the foreman, so it is not a field instruction yet.Due Oct 2
- Written answer on the concealed duct conflict, WO-3108Anjali Venkataraman. No crew hours go on the event until it is recorded.Due Oct 6
- Curb supply answer, crane and water heater venting confirmationsBrackenhurst, with the roofing contractor. The rooftop unit lines stay at 12 of 14 confirmed until then.Due Oct 7
- Recorded responses on the air handling unit and the hydronic pumpsBrackenhurst project manager, from the design team. Both are past the window.Due Oct 8
- Closeout items accepted or returnedBrackenhurst closeout coordinator, within 5 business days of each item.As received
- Two alternates accepted at awardEnergy recovery on the rooftop units and variable frequency drives on the hydronic pumps.Received