What Ironvale needs from Brackenhurst to close the open answers, why, and by when. Upload straight into the request.

5 requests open
  • Ceiling grid RFI answer, resent through the recordBrackenhurst project manager. The email answer went to the foreman, so it is not a field instruction yet.Due Oct 2
  • Written answer on the concealed duct conflict, WO-3108Anjali Venkataraman. No crew hours go on the event until it is recorded.Due Oct 6
  • Curb supply answer, crane and water heater venting confirmationsBrackenhurst, with the roofing contractor. The rooftop unit lines stay at 12 of 14 confirmed until then.Due Oct 7
  • Recorded responses on the air handling unit and the hydronic pumpsBrackenhurst project manager, from the design team. Both are past the window.Due Oct 8
  • Closeout items accepted or returnedBrackenhurst closeout coordinator, within 5 business days of each item.As received
  • Two alternates accepted at awardEnergy recovery on the rooftop units and variable frequency drives on the hydronic pumps.Received

File requests

Each request shows what it unblocks and its due date. Your team uploads directly, and Marguerite checks it against the record.
Open in File Request